ICN 248th Masjid Project Updates
The WALLS are UP 8.15.2023
Basement Structure Complete
7.5.2023
Steel infrastructure complete 7.21.2023
Footings and Foundations for the building complete 6.27.2023
Foundations for the south end of the building complete 6.6.2023
Concrete Pour in footings & Stormwater pipes install 5.10.2023
Forms of basement walls installed for concrete pour 6.2.2023
Footings & Foundation – Masjid Basement 5.4.2023
Qibla Direction Confirmed 4.27.2023
Excavation for Masjid basement 4.20.2023
Footing & Foundation permit approved and released
Sanitary Sewer Pipe Install & Masjid Basement Excavation 4.24.2023
Structural Steel Fabricated 4.8.2023